Share of US electricity used by data centers in 2023, and the high-end projection for 2028 (low case: 6.7%).
Lawrence Berkeley National Laboratory: 2024 Report on U.S. Data Center Energy UseThe AI economy is being built one permit, one substation and one county vote at a time.I track all three.
Data Center Development Watch is my weekly read on where North America is actually building: siting, power, permits, incentives, and the community fights that decide what gets built. Every claim links to the filing, order or report behind it. One national edition, plus the regional tracks you care about.
Presented by
Demand is not the question anymore. Power, permission and patience are.
2026 capital spending forecast by Alphabet, Amazon, Meta and Microsoft combined, earmarked largely for data centers and the gear inside them.
Bloomberg via Data Center Knowledge: Big Tech 2026 capital spendingLarge-load requests in ERCOT's queue in mid-2026, nearly 89% tied to data centers.
ERCOT large-load queue (Data Center Frontier)Under construction in Atlanta, which passed Northern Virginia as North America's top construction market for the first time.
CBRE H1 2026: Atlanta construction marketIndiana counties with data center moratoriums, plus three that have banned projects outright.
Indiana county restrictions (The Bond Buyer)Data center load that has asked to connect to Alberta's grid since the province set a C$100B investment goal.
Alberta market overview (Baxtel)This is not a real estate story. It is a leadership story.
Most coverage treats data centers as a land deal or a tech headline. From where I sit, it is something else: the largest test of operating leadership in a generation, playing out in county meeting rooms, utility commissions and interconnection queues.
Three things now decide whether a project is real. Power: who can deliver megawatts, when, and who pays for the wires. Permission: zoning, tariffs, incentives and the community's consent. Patience: the years between an announcement and an energized building, where capital, contractors and politics all move.
Every week I read the filings, orders and reports so you do not have to, and I tell you what changed, what it means, and the next date to watch.
Michael Ryan BetzRecent reads
The world's largest data center market just closed for a year
Loudoun freezes, Google brings its own gigawatt, Taylor's playbook, Wisconsin's statewide review, and California shuts the door.
The new gatekeeper is the tariff
The fastest-moving filter on data center growth is not zoning. It is the large-load tariff.
The fastest-moving filter on data center growth is not zoning. It is the large-load tariff. In Ohio, regulators approved AEP Ohio's rule requiring new data centers above 25 MW to pay for at least 85% of their subscribed capacity for up to 12 years, whether they use it or not PUCO via POWER Magazine. In Oregon, the POWER Act created a separate rate class, and regulators approved a 29.7% increase for Portland General Electric's large-load customers while residential rates dipped OPB. In Québec, Hydro-Québec has proposed a dedicated rate of roughly 13 cents per kWh for data centers above 5 MW, about double the current large-power rate BLG.
What it means: tariffs separate committed projects from speculative ones. If your state does not have one yet, expect a filing. If you are a developer, model the minimum-bill exposure before you announce.
A queue is not demand
Headline megawatts are options, not buildings. The queue tells only part of the story.
ERCOT's large-load queue went from 63 GW at the end of 2024 to about 226 GW by November 2025 Latitude Media, then past 438 GW by mid-2026 Data Center Frontier. Texas has never used more than about 86 GW at once. Georgia shows the other side: in one quarter, 14.3 GW of projects left Georgia Power's large-load pipeline even as new ones arrived Utility Dive.
What it means: headline megawatts are options, not buildings. That is why every major project in this briefing gets a Reality Score: how much of it is power secured, land controlled, permits filed and a named end user.
The moratorium map is the new site-selection map
Community consent is now a line item. The projects that win show up early with answers.
Local opposition blocked or delayed at least 75 US projects worth about $130 billion in Q1 2026, roughly matching all of 2025 in one quarter Data Center Watch. Another 45 projects worth about $68 billion followed in Q2 Tom's Hardware. In Indiana, 25 of 92 counties now have moratoriums The Bond Buyer. Even Loudoun County, Virginia, the world's largest market, is weighing a pause of up to a year on new data center and substation applications Loudoun County.
What it means: community consent is now a line item. The projects that win show up early with water, noise, tax and grid answers, not after the vote.
One national edition. Twelve regional tracks.
Everyone gets the National edition. Add the regions where you build, invest, govern or sell, and you'll get that region's developments, filings and dates in your briefing.
National Trends
US + CanadaSignal: Data centers used 4.4% of US electricity in 2023 and could use up to 12% by 2028.
Northeast
NY, New EnglandWatching: Tight grids and high power prices make the Northeast a test of on-site generation and grid-friendly design.
Mid-Atlantic
VA, MD, PA, NJ, DE, DCSignal: Northern Virginia vacancy sits at 0.2% while Loudoun weighs a pause, and Pennsylvania's Homer City site plans up to 4.5 GW of gas generation for a campus.
Southeast
GA, NC, SC, FL, TN, ALSignal: Georgia regulators approved nearly 9,885 MW of new generation, largely for data centers, and Atlanta now leads North American construction.
Midwest
OH, IN, IL, MI, WI, MN, KYSignal: Ohio set the template for large-load tariffs, while a quarter of Indiana's counties have paused projects.
Plains
IA, NE, KS, MO, DakotasSignal: FERC approved SPP's fast-track process to study large loads paired with new generation in about 90 days.
South Central
TX, OK, LA, AR, MSSignal: ERCOT is tracking 438 GW of large-load requests, and Meta is expanding its Louisiana Hyperion campus to 5 GW and more than $50B.
Southwest
AZ, NM, NVSignal: Arizona paused the incentives that fueled its boom for three years as water and power concerns grew.
Mountain West
CO, UT, WY, ID, MTSignal: Laramie County approved Project Jade near Cheyenne: 1.8 GW at the start, designed to scale toward 10 GW.
West Coast
CASignal: Silicon Valley vacancy keeps falling as demand outruns supply in one of the hardest places in America to build.
Pacific Northwest
OR, WASignal: Oregon's POWER Act moved data centers into their own rate class: +29.7% for large loads, a small cut for households.
Western Canada
BC, AB, SK, MBSignal: Alberta is courting C$100B of AI data centers, and Meta broke ground on its first Canadian campus in Sturgeon County.
Central & Atlantic Canada
ON, QC, Atlantic provincesSignal: Hydro-Québec proposed roughly doubling the power rate for data centers over 5 MW.
DC Watch Supplier Intel
For contractors, trades, suppliers, staffing firms and service companies. Regional project stage tracking and procurement readiness guidance.
The Reality Score
Announcements are cheap. Every major project in the briefing gets a Reality Score so you can tell a campus from a press release.
- 01
Power secured
Signed service agreement, interconnection position or on-site generation
- 02
Land and zoning
Site control and approvals in hand
- 03
Permits filed
Air, water, building and utility filings on record
- 04
Named end user
A hyperscaler, AI lab or tenant on the record
- 05
Money and momentum
Financing, contractors and construction activity
Scores are my editorial judgment from public records, not investment advice.
Dates to watch
Get the briefing built for your map.
- Weekly, free, about a 6 minute read
- Every claim linked to its source
- National edition plus your regional tracks
- Unsubscribe anytime
Selling into data center projects? Explore Supplier Intel and join the founding list.

The Proper Group is a collective of 200 vetted fractional and interim executives who embed inside companies to lead through growth, change and large projects, including data center and infrastructure work.
From site selection and incentives to power, permitting and the build team, The Proper Group places seasoned executives to lead the work.
Sponsor or partner with the briefing
Reaching developers, utilities, economic developers, investors and site selectors across the US and Canada.
Sources & further reading
Figures are as reported by each source on the date published. Spot an error? Email michael@michaelryanbetz.com.